| Ready for Tendering & Execution | | |
| |
-
1977: Finishing construction of Tarik dam and Powerhouse building
-
2003: Review of second phase studies for powerhouse equipment by Armandab Co.
-
2007: Preparing tender document, EPC method, by Tehran-Berkly Consulting Engineers
| |
|
Studies of Yasuj Chain Projects began in 1989 by Ministry of Jihad with cooperation of Chinese Research Institute (ECHIDI). In primary studies, a reservoir dam had been predicated that was cancelled due to complicated situation of geology and technical problems. During next phase of studies several options were taken into consideration and finally the option of nine chain power plants with the capacity of 20 MW was approved by the client and its complementary studies were carried out
Construction activities of six of these power plants which had economic priority began. Krick 1 and Polklu 1 power plants were put into operation in 1994 and 2004. Construction activities of Krick 2 and krick 3 power plants ended in 2006. Polklu 2 and Kakhdan power plants were also tested and put into operation in June 2007. In 2007 tender documents of Yasuj Development Project including 3 remaining power plants were prepared by Dezab Consulting Engineers. Power plants of Yasuj chain projects are as follows:
-
Kahgol
-
Cheshmemishi
-
Cheshmemishi and Kahgol Joint Power Plant
|
| | |
-
1970 Construction of Zayanderud regulating dam by the group of Campnon Bernard & Byar and Sogreah Consulting Engineers from France
-
1991 Proposal of Esfahan Regional Water Organization to purchase power plant equipments for Zayanderud regulating dam
-
1996 Transfer of studies of the project in form of one of the twelve projects of Small Hydroelectric Power Plants to Ghods Niru Consulting Engineers
-
2001 Transfer of the first and second phases of studies to Moshanir Consulting Engineers by IWPC as the Client of the Project
-
2003 Presenting reports of the first phase studies by Moshanir Consulting Engineers
-
2004 Finalization of location of power station in left bank of Zayanderud River
-
2005 Delivering the second phase reports and tender documents of power station by consultant to the client
-
2006 Conclusion of consultancy contract, preparation of tender documents and construction of EPC with Moshanir Consulting Engineers
-
2007 Tendering process of the project in form of design and construction and selecting the contractor
-
2008 Negotiation with elected contractor to execute the project via EPCF method
|
|
|
|
|