The studies were carried out by Jihad Ministry Commencement of construction activities: 1986 Operation commencement: 1989 | |
The studies were carried out by Civil Works and Village Industries Deputy of Jihad Ministry Commencement of construction activities: 1986 Operation commencement: 1986 | |
The studies were carried out by civil Works and Village Industries Deputy of Jihad Ministry in 1996 Operation commencement: 2000 | |
The studies were carried out by Jihad Ministry Commencement of construction activities: 1992 Operation commencement: 1999 | |
Before 1941: Designing 3 tunnels for transferring Koohrang River from main stream of Karun to the stream of Zayandeh Rud and central plains of Iran according to the previous studies 1943 to 1948: Construction of Koohrang River first tunnel with the length of 200 m and discharge capacity of 22 m3/s and annual water transfer of 300 million m3 1975 to 1985: Construction of Koohrang River second tunnel with the length of 2050 m and discharge capacity of 44 m3/s with annual water transfer of 300 million m3 1983: Beginning of first phase studies of Koohrang Power Plant by Moshanir Co. after proposal of Esfahan Regional Water Organization and approval of Ministry of Energy; to construct a power plant with the capacity of 35 MW at the outlet of second tunnel, according to the studies 1988: Beginning of second phase studies by Moshanir Co. and Soil Mechanic Consulting Engineers (due to geotechnical problems Soil Mechanic Consulting Engineers gave up continues of studies) 1991: Beginning of construction activities in culvert section by the team of Esfahan Regional Water Organization and beginning of designing and studies of powerhouse by LIF Co. 1998: Transferring of project from Esfahan Regional Water Organization to Iran Water and Power Resources Co. 1999: Concluding second phase studies and proposals of foreign consultant with cooperation of Moshanir Co. Beginning the tendering process of the powerhouse building and outlet channel and selecting Kanio Co. as the contractor 2001: Beginning of construction activities of project by Kanio Co. 2004: Completing all construction activities of the project, inauguration and operation of powerhouse in January of the same year | |
Basic studies of the Lavarak project, with the capacity of 47 MW in form of taking advantage from Lar dam equipments and its diversion tunnels, was carried out by Alexander Gip and Organic Consulting Engineers. This project was approved in 1975. In 1977 access tunnel to powerhouse cavern was completed with the length of 1000 m for geotechnical tests. In 1980 Lar dam water transition through pipe lines and tunnels with the length of 3 kilometer to Latian dam lake and finally to Tehran became necessary. In 1981 the project was handed over to Lar Consulting Engineers. In 1984 the geotechnical complementary tests (excavation of trenches, sampling and in-the-field tests) was carried out by Japanese Komogaigomo Co. In 1997 Australian Smec Co. started cooperating with Lar Consulting Engineers. 1n 2000 the project was handed over to Iran Water and Power Resources Development Co. and the studies were followed more rapidly. In 2001 the documents were reviewed and tender documents were prepared in form of three main contract In 2002 construction activities began by Hara Institute including excavation of access tunnel to cavern crest, penstock and ventilation shafts... | |
1998: Jihad Ministry puts in his agenda electricity generation through renewable energies in distant villages of the country 1999: Beginning of basic studies with first priority of seven power plants 2003: Construction of seven power plants by Jihad Ministry 2004: Tendering process and completion of five power plants by Iran Water and Power Resources Development Co.
Power plants of Micro Project are as follows:
- Karnagh
- Garni
- Darjan
- Maran
- Nav
| |
During 1989-1991 phase one studies were carried out by Pajuhesh Niru Co. In 1998 surveying activities of second phase was carried out by Jihad Engineering Service Co. First phase review and second phase studies were carried out by Pars Piab Co. In 1999 geotechnical studies of the project was carried out by Bon Pajuh Co. In 2000 second phase survey activities was completed by Pars Piab Co. In 2004 tendering process and determining main contractor of the project should have been carried out, but due to non-ensuring of necessary guaranties from the contractor side, inevitably the contract was cancelled. In 2007 technical specifications of tender documents were reviewed by sakku Consulting Engineers and the main contractor was selected. | |
The studies were carried out Jihad Ministry Commencement of construction activities: 1985 Operation commencement: 1987 | |
The studies were carried out by Jihad Ministry Commencement of construction activities: 1991 Operation commencement: 1995 | |
Basic studies of power station, as a part of Shahid Rajaee Project, began by the Mahab Qoads Consultant and Electrowatt Stoki Co. of Sweden since 1989 together with the studies of dam body. The second phase studies were completed in 1994. The capacity of this project is 13.5 MW (three units of 4.5 MW). In the middle of 2000 this project was taken from Regional Water Organization of Mazandaran and handed over to Iran Water and power resources Development Co. The studies of technical documents and preparing tender documents continued with cooperation of Mahab Qods Co. In the second half of 2001 Pajuhab Co, as the project consultant and then Armetab Co. as the civil contractor and Mabna Niroo Co. as the contractor of preparing, manufacturing and installation of switchyard equipments were elected through tendering and their activities began in March 2002. In July 2002 due to an earthquake in the region the main part of these activities came to a halt. In February 2004 the main contract of project was concluded with Farab Co. and up to now the project’s different phases are being implemented. | |
The studies were carried out by Jihad Ministry Commencement of construction activities: 1991 Operation commencement: 1994 | |
Studies of the Yasuj Chain Project began in 1989 by Jihad Ministry and cooperation of Chinese Research Institute (ECHIDI). In basic studies construction of a reservoir dam had been predicted which was cancelled due to complex geological situation and technical difficulties. In further studies several other options were studied and finally the option of nine chain power plants with the capacity of 20 MW was approved by the client. Construction activities of six of these nine power plants which had economical priority began. Karick1 and Polkolu1 were completed and put into operation in 1994 and 2004. Construction activities of Karick2 and Karick3 were also finished in 2006. Two power plants of Polkolu2 and Kohkdan were also tested in June 2007 and put into operation.
Power plants of Yasuj Chain Project are as follows:
- Polkolu1
- Polkolu2
- Kokhdan
- Karick1
- Karick2
- Karick3
|
|
|
|
|
|
|
|