Skip to main content
شرکت توسعه منابع آب و نیروی ایران
Main Page
About us
Statements
Company Managers
Projects
Partner Companies
GoAdvanced Search

 Being Operated
 expandArdeh Power PlantCapacity (MW): 0.125Scale:   micro
 expandDarre Takht 1 Power PlantCapacity (MW): 0.68Scale:   mini
The studies were carried out by Civil Works and Village Industries Deputy of Jihad Ministry
Commencement of construction activities: 1986
Operation commencement: 1986
 expandDarre Takht2 Power PlantCapacity (MW): 0.9Scale:   mini
 expandGamasiab Power PlantCapacity (MW): 2.8Scale:   small
The studies were carried out by Jihad Ministry
Commencement of construction activities: 1992
Operation commencement: 1999
 expandKuhrang Power PlantCapacity (MW): 35Scale:   medium
 expandLavarak Power PlantCapacity (MW): 47Scale:   medium
Basic studies of the Lavarak project, with the capacity of 47 MW in form of taking advantage from Lar dam equipments and its diversion tunnels, was carried out by Alexander Gip and Organic Consulting Engineers. This project was approved in 1975.
In 1977 access tunnel to powerhouse cavern was completed with the length of 1000 m for geotechnical tests.
In 1980 Lar dam water transition through pipe lines and tunnels with the length of 3 kilometer to Latian dam lake and finally to Tehran became necessary.
In 1981 the project was handed over to Lar Consulting Engineers.
In 1984 the geotechnical complementary tests (excavation of trenches, sampling and in-the-field tests) was carried out by Japanese Komogaigomo Co.
In 1997 Australian Smec Co. started cooperating with Lar Consulting Engineers.
1n 2000 the project was handed over to Iran Water and Power Resources Development Co. and the studies were followed more rapidly.
In 2001 the documents were reviewed and tender documents were prepared in form of three main contract
In 2002 construction activities began by Hara Institute including excavation of access tunnel to cavern crest, penstock and ventilation shafts...
 expandMicro Power PlantCapacity (MW): 0.227Scale:   micro
 expandPiran Power PlantCapacity (MW): 8.4Scale:   small
During 1989-1991 phase one studies were carried out by Pajuhesh Niru Co.
In 1998 surveying activities of second phase was carried out by Jihad Engineering Service Co. First phase review and second phase studies were carried out by Pars Piab Co.
In 1999 geotechnical studies of the project was carried out by Bon Pajuh Co.
In 2000 second phase survey activities was completed by Pars Piab Co.
In 2004 tendering process and determining main contractor of the project should have been carried out, but due to non-ensuring of necessary guaranties from the contractor side, inevitably the contract was cancelled.
In 2007 technical specifications of tender documents were reviewed by sakku Consulting Engineers and the main contractor was selected.
 expandSarrud Power PlantCapacity (MW): 0.065Scale:   micro
 expandShahid Azimi Power PlantCapacity (MW): 1Scale:   small
The studies were carried out by Jihad Ministry
Commencement of construction activities: 1991
Operation commencement: 1995
 expandShahid Rajaee Power PlantCapacity (MW): 13.5Scale:   medium
 expandShahid Talebi Power PlantCapacity (MW): 2.25Scale:   small
The studies were carried out by Jihad Ministry
Commencement of construction activities: 1991
Operation commencement: 1994
 expandYasuj Chain Power PlantsCapacity (MW): 16.8Scale:   small

Visit: