Tarik Power Plant
History and background
  • 1977: Finishing construction of Tarik dam and Powerhouse building
  • 2003: Review of second phase studies for powerhouse equipment by Armandab Co.
  • 2007: Preparing tender document, EPC method, by Tehran-Berkly Consulting Engineers
Targets
Annual generation of 16.46 million kwh of energy
Location
The project is located in 3658 of geographical latitude and 4935 of geographical longitude in Gilan Province, with approximate distance of 35 km downstream of Sefidrud Dam on Sefidrud River
Technical Information

Dam Body
Type: Rockfill-Concrete
Height: 22 m
Crest length: 380 m (250 m concrete and 130 m rockfill)
Spillway type: Compound gated
Numbers of gates: 9 moving gates with dimensions of 15*5.5

Powerhouse
Type: Reservoir
Building: 3 floors concrete with dimensions of 34*20*19 m
Discharge of each unit: 19 m3/s
Head: 8.5 m
Installation capacity: 2.8 MW
Network type: Public
Turbine type: Kaplan
Numbers of units: 2
Power of generator: 1.8 Mva
Generator voltage: 6.3 Kv
Frequency: 50 Htz
Generator speed: 750 rotations/minute
Numbers of main transformer: 1
Transformer power: 5 Mva
Alteration ratio: 6.3 to 20 Kv
Type of post: Indoor

 
Forebay:
Type: concrete
Volume: 1900 m3
Dimensions: 19*26 m