Shahid Talebi Power Plant
History and background
The studies were carried out by Jihad Ministry
Commencement of construction activities: 1991
Operation commencement: 1994
Targets
  • Annual generation of 13.4 million kwh of energy
Location
The project is located in 30°17¢ of geographical latitude and 51°29¢ of geographical longitude in Fars Province, Sepidan City
Technical Information

  • Diversion dyke
    Type: Concrete
    Spillway height: 4.5 m
    Spillway length: 11 m
  • Water transfer channel
    Type: Pipe and reinforced concrete
    Length: 1967 m
    Dimensions: 1.8*2 m
  • Forebay:
    Volume: 300 m3
    Dimensions: 3.1*8*12 m
  • Penstock
    Type: Steel
    Numbers: 3
    Diameter: 0.76 m
    Length: 3*279 m
    Powerhouse
    Type: Current On-the-ground
    Building: Concrete structure with the dimensions of
    5.7*13*28 m
    Total design discharge: 2.75 M3/s
    Head: 105 m
    Installation capacity: 2.25 MW
    Network type: Public
    Turbine type: Horizontal Francis
    Numbers of units: 3
  • Outlet channels
    Type: Reinforced concrete
    Dimensions: 2*20 m
 