Turn on more accessible mode
Skip to main content
Turn off more accessible mode
Iran Water and Power Resources Development Co.
Sign In
|
فارسی
Main Page
About us
Statements
Company Managers
Projects
Partner Companies
Company Introduction
Articles of Association
Organizational Structure
Major Targets
Achievements
Quality Management System
Vision
Mission
Moral Values
Quality Policy
Board of Managers
General Manager
Deputies
Project Managers
Office Directors
Previous General Managers
Project Layouts
Projects at One Glance
Major Hydropower (Being Operated)
Major Hydropower (Being Executed)
Major Hydropower (Being Studied)
Small and Medium Hydropower
Karun 3
Karkhe
Masjed Soleiman
Bakhtiari
Khersan 3
Rudbar Lorestan
Siahbishe
Seimare
Karun 4
Gotvand
Main Consultants
Main Contractors
Iran Water and Power Resources Development Co.
>
News
>
IWPC's Fifth External Survey Finalized
News
: IWPC's Fifth External Survey Finalized
Title
IWPC's Fifth External Survey Finalized
Text
The fifth external survey of IWPC, based on the ISO9001: 2008 standard requirements, undertaken by DNV institute, was finalized in Feb 24, 2010.
In the closing ceremony of the survey, the results were presented in the presence of managing director, deputies, executives and managers of the projects.
The most important findings in this period are announced as followed:
1-Observation: 3 cases, such as lack of setting a follow-up system for corrective measures and defined recommendations in the monitoring report, no specific definition for general contractor in the company and how to evaluate, select and approve them.
2- Recommendations for improving the 4 cases include:
2-1- Creating an integrated risk management system in the company
2-2- Defining an appropriate mechanism for recording, announcing the experiences and learned lessons in the form of the project 's report and sharing them in the company
2-3- To be ensured about the non-interference of defined indicators in various systems such as BSC and quality management
2-4- Reviewing the complementary and specialized check lists for internal surveys
3- Lack of conformity: It was not observed
4- Positive points: several positive points were observed in the field of evaluating the risk of projects' budget, preparing ACT Master Plan
At the end of the meeting, Eng. Mozaffari, Manager Director of the company, appreciated the efforts undertaken by survey group, as well as company's colleagues.
He also underlined the necessity of following up the findings in the form of observations, as well as improving the field of risk management.
Source
Subject
Expiry Date
Priority
Normal
News Link
Priority Sequence
2
Relevant Link
Relevant Site
Iran Water and Power Resources Development Co.
Attachments
2.jpg
Content Type:
Announcement
Created at 3/2/2010 1:17 PM by mohammad-alireza
Last modified at 3/2/2010 1:17 PM by mohammad-alireza
Use this page to add attachments to an item.
Name
Visit:
[
Frequently Asked Questions
] [
Proposals and Critiques
] [
Opinion Poll
] [
Site Map
]
[
Links
] [
Cooperation Request
] [
Contact Us
]